Under the agreement with Guangdong Kenuo Electric Power Geotechnical Engineering Co.,ltd. the company has undertaken the project of data acquisition, DOM and DEM generation for the 500kv power line selection from Xianling Mountain to Huadu and Yandu.
In order to meet the timeline for design, the company had made the data acquisition and processing simultaneously. The data of 132km of Xianling—Huadu has already been handed into the customer. The rest is still in process and expected to be finished within two or three weeks.ruction in northern China.na.